Points this exam keeps coming back to
- Before a line is opened it is isolated, then drained, purged and cleaned, then gas tested.
- Flange bolts are cracked from the 5 o’clock position, with the body to the side.
- Excavations are protected by benching, sloping or shoring, with spoil at least 0.6 m (2 ft) from the edge.
- Any part of the body breaking the plane of an opening is confined space entry. The standby man logs every entrant in and out.
- Before heavy equipment works, the issuer checks the operator’s certificate and safe clearance.
Frequently asked questions
Is putting an arm through a manway confined space entry?
Yes. Any part of the body that breaks the plane of the opening counts as entry, so the confined space permit applies.
What does the standby man do in an emergency?
He calls the rescue team. He does not go into the space himself.
Why is spray painting more dangerous inside a confined space?
The solvent vapour builds up in the enclosed space and can make the atmosphere flammable or explosive.
More Aramco WPR exams
- All Aramco WPR exams
- Exam 1: Permits and certificates
- Exam 2: Joint site inspection
- Exam 3: Gas, excavation, stop-work
- Exam 4: Lockout and isolation
- Exam 5: Confined space
- Exam 6: Restricted areas
- Exam 7: Gas testing, H2S, excavation
- Exam 8: Height, PPE and lockout
- Exam 9: Confined space and permits
- Exam 10: Permit rules and stop-work
Unofficial practice for training only. This site is not affiliated with Saudi Aramco, and these are not official exam questions.