The second half of the Hazard Recognition book is where the numbers live, and the test likes them: when a lift becomes critical, how far a truck stays from an excavation edge, how far sewers are sealed around hot work, what to do when an H2S alarm goes off.
This exam covers Modules 5 to 11: heavy equipment, excavations and shoring, hazardous materials, hydrogen sulfide, fires and explosions, emergency preparations, and the review activities at the end of the book.
Loading the exam (30 questions)…
Numbers worth having in your head
- A lift is critical above 40 tons, above 85% of the crane’s rated capacity, or within 10 m (33 ft) of hydrocarbon or pressurized piping.
- Keep vehicles back from an excavation by 2 m or the depth of the excavation, whichever is greater. Spoil at least 60 cm (2 ft) from the edge.
- Hand dig for at least 3 m (10 ft) toward a located live cable.
- Cover or water-seal sewers within 23 m (75 ft) of hot work ignition sources.
- On an H2S alarm, leave at once, crosswind and uphill if you can.
Frequently asked questions
When is a crane lift a critical lift?
The course gives several triggers. The lift is critical if the load is over 40 tons, over 85% of the crane's rated capacity, or the boom works within 10 m of hydrocarbon or pressurized piping. Any one of them is enough.
Which way do you go when an H2S alarm sounds?
Out immediately, crosswind and uphill if you can, and stay out until your personal monitor reads clean. H2S is heavier than air and your sense of smell stops working at high levels, so never walk towards the smell.
How close can a truck park to an excavation?
Keep vehicles and heavy equipment back by 2 m or the depth of the excavation, whichever is greater. For a 3 m deep trench that means at least 3 m.
How long is this exam?
30 questions with a 60-minute timer. One needs more than one answer. You need 85% to pass.